Solomon Project
Fortescue Metals Group Ltd
Solomon Project – Firetail & Kings Valley Mine sites
Client
RCR Tomlinson Ltd
Services
3D Steel Detailing services
Project Management Consultancy
Schedule
May 2012 - Sept 2012
Execution
BIM Drafting Services provided the 3D modelling and steel detailing service for the Solomon Project for Fortescue Metals Group Ltd in an unprecedented timeframe, delivering approximately 6000 Tonnes of modularized structural, mechanical, and platework steel within 120 days.
Working seamlessly with the design team to release drawings for fabrication as soon as the design was finalized allowed the fabricator to meet stringent shipping dates. The combination of BIM Drafting Services providing experienced project managers, coordinators, schedulers, employing essential change control systems and a team of over 140 resources enabled us to beat the schedule in high priority areas